[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118486":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1118486,789,1,"单选题","某项目编制施工成本计划时，先将成本按分部分项工程进行了划分，又根据施工实施阶段计划将各分部分项工程成本按月汇总进行编制，形成各月成本支出计划，这种编制方法属于()。 A.按施工成本组成编制施工成本计划",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","按子项目组成编制施工成本计划",false,{"key":16,"text":17,"correct":14},"B","按工程实施阶段编制施工成本计划",{"key":19,"text":20,"correct":21},"C","上述",true,{"key":23,"text":24,"correct":14},"D","B两种方法的综合运用","2021\u002F2020教材P107页 三、按工程实施阶段编制施工成本计划的方法；题设中实际上是在描述按工程进度编制施工成本计划的过程，虽然有将成本按分部分项工程进行划分的过程，但不属于按子项目组成编制施工成本计划，也不属于A、B两个方法的应用，所以选项A、B、D均不对。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]