[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118483":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1118483,789,1,"单选题","某混凝土搅拌机的台班产量为800m3，与之配合的工人小组有4人，则人工定额为()。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","0.2工日\u002Fm3",false,{"key":16,"text":17,"correct":14},"B","0.5工日\u002Fm3",{"key":19,"text":20,"correct":14},"C","0.2工日\u002F100m3",{"key":22,"text":23,"correct":24},"D","0.5工日\u002F100m3",true,"2021\u002F2020教材P63页 人工定额按表现形式的不同，可分为时间定额和产量定额两种形式。单位产品时 间定额（工日）=小组成员工日数总和机械台班产量=4800=0.005工日m3=0.5工日100m3。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]