[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118481":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1118481,789,1,"单选题","下列建设工程项目进度控制的措施中，属于技术措施的是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","优选工程项目施工方案",true,{"key":16,"text":17,"correct":18},"B","确定各类进度计划的审批程序",false,{"key":20,"text":21,"correct":18},"C","选择合理的合同结构",{"key":23,"text":24,"correct":18},"D","选择工程承包发包模式","2021\u002F2020教材P100页 2.技术措施施工过程中降低成本的技术措施，包括如进行技术经济分析，确定最佳的施工方案。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]