[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118473":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1118473,789,1,"单选题","人工定额的编制，主要包括（ ）两项工作。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","拟定正常的施工条件以及拟定定额时间",true,{"key":16,"text":17,"correct":18},"B","拟定定额数量以及拟定产品质量",false,{"key":20,"text":21,"correct":18},"C","拟定施工的正常条件以及拟定定额数量",{"key":23,"text":24,"correct":18},"D","拟定施工的正常条件以及拟定产品质量","2021\u002F2020教材P60页 编制人工定额主要包括拟定正常的施工条件以及拟定定额时间两项工作，但拟定定额时间的前提是对工人工作时间按其消耗性质进行分类研究。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]