[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118472":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1118472,789,1,"单选题","某地下工程合同约定，计划1月份开挖土方80000立方米，2月份开挖160000立方米，合同单价均为85元\u002F立方米；计划3月份完成混凝土工程量500立方米，4月份完成450立方米，合同单价均为600元\u002F立方米。而至各月底，经确认的工程实际进展情况为，1月份实际开挖土方90000立方米，2月份开挖180000立方米，实际单价均为72元\u002F立方米；3月份和4月份实际完成的混凝土工程量均为400立方米，实际单价700元\u002F立方米。至3月底，该工程的费用绩效指数(CPI)为()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","0.800",false,{"key":16,"text":17,"correct":18},"B","1.176",true,{"key":20,"text":21,"correct":14},"C","0.857",{"key":23,"text":24,"correct":14},"D","1.250","2021\u002F2020教材P112页 费用绩效指数CPI=BCWP\u002FACWP=（90000×85+180000×85+400×600）\u002F（90000×72+180000×72+400×700）=1.176。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]