[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118471":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1118471,789,1,"单选题","某建筑公司承担一大学新校区工程项目的施工任务，主要项目有图书馆、教学楼学生宿舍等。在进行工程项目竣工成本综合分析时，可作为成本核算对象的是()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","新校区工程项目",false,{"key":16,"text":17,"correct":14},"B","单项工程，如图书馆、教学楼、学生宿舍",{"key":19,"text":20,"correct":21},"C","单位工程，如图书馆工程",true,{"key":23,"text":24,"correct":14},"D","分部工程，如图书馆打桩工程","2021\u002F2020教材P123页 单位工程通常是指具有独立施工条件的工程，因此，施工项目竣工成本的综合分析应以单位工程作为成本核算的对象",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]