[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118470":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1118470,789,1,"单选题","进行施工成本控制，工程实际完成量、成本实际支出等信息的获得，主要是通过()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","工程承包合同",false,{"key":16,"text":17,"correct":14},"B","施工成本计划",{"key":19,"text":20,"correct":21},"C","进度报告",true,{"key":23,"text":24,"correct":14},"D","施工组织设计","2021\u002F2020教材P109页 因为工程实际完成量、成本实际支出等信息，反映的是工程进展的实际状况，由进度报告反映，所以选C。工程承包合同、施工成本计划和施工组织设计主要反映施工的计划信息。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]