[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118466":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1118466,789,1,"单选题","某工程施工期间，因承包人原因导致工期延误，且在延误期内国家相关政策发生变化，由此引起的合同价款调整，应该（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","调增的和调减的均予以调整",false,{"key":16,"text":17,"correct":14},"B","调增的和调减的均不予调整",{"key":19,"text":20,"correct":21},"C","调增的不予调整，调减的予以调整",true,{"key":23,"text":24,"correct":14},"D","调增的予以调整，调减的不予调整","2021\u002F2020教材P78页 因承包人原因导致工期延误，且上述规定的调整时间在合同工程原定竣工时间之后，合同价款调增的不予调整，合同价款调减的予以调整。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]