[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118458":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1118458,789,1,"单选题","某工程施工至2016年6月底，已完工程预算费用(BCWP)为600万元，已完工程实际费用(ACWP)为800万元，计划工程预算费用(BCWS)为700万元，则该工程此时的偏差情况是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","费用节约，进度提前",false,{"key":16,"text":17,"correct":18},"B","费用超支，进度拖后",true,{"key":20,"text":21,"correct":14},"C","费用节约，进度拖后",{"key":23,"text":24,"correct":14},"D","费用超支，进度提前","2021\u002F2020教材P112页 费用偏差(CV)=已完工程预算费用(BCWP)已完工程实际费用(ACWP)=600－800=-200万元；当CV＞0时，说明工程费用节约；当CV＜0时，说明工程费用超支。进度偏差(SV)=已完工程预算费用(BCWP)－计划工程预算费用(BCWS)=600－700=-100万元；当SV＞0时，说明工程进度超前；当SV＜0时，说明工程进度拖后。故该工程费用超支，进度拖后。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]