[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118455":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1118455,789,1,"单选题","在工程成本执行过程中，最理想的状态是（）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","已完工作实际费用、计划工作费用、已完工作预算费用三曲线靠的很近，平稳上升。",true,{"key":16,"text":17,"correct":18},"B","已完工作实际费用、计划工作费用靠的很近,已完工作预算费用靠的很远。",false,{"key":20,"text":21,"correct":18},"C","已完工作实际费用、已完工作预算费用靠的很近,计划工作费用靠的很远。",{"key":23,"text":24,"correct":18},"D","计划工作费用、已完工作预算费用三曲线靠的很近，已完工作实际费用靠的很远。","2021\u002F2020教材P114页 最理想状态是已完工作实际费用、计划工程预算费用和已完成工作预算费用三条曲线靠得很近、平稳上升，表示项目按预定目标计划进行。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]