[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118454":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1118454,789,1,"单选题","某地下工程施工合同约定，计划2月份开挖160000m3，合同单价均为85元\u002Fm3。到2月底，经确认实际开挖土方180000m3，实际单价为72元\u002Fm3，则该工程的以工作量表示的进度偏差（SV）为（）万元。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","234",false,{"key":16,"text":17,"correct":14},"B","-234",{"key":19,"text":20,"correct":21},"C","170",true,{"key":23,"text":24,"correct":14},"D","-170","2021\u002F2020教材P112页 进度偏差SV=已完工作预算费用（BCWP）-计划工作预算费用（BCWS），所以该工程以工作量表示的进度偏差SV=85×（180000-160000）=170万元。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]