[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118452":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1118452,789,1,"单选题","“时间一成本累积曲线”的特征是( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","每个工程只有一条“时间～成本累积曲线”",false,{"key":16,"text":17,"correct":18},"B","每一条“时间一成本累积曲线”都对应某一特定的工程进度计划",true,{"key":20,"text":21,"correct":14},"C","“时间一成本累积曲线”是按最早开始时间编制所形成的曲线",{"key":23,"text":24,"correct":14},"D","“时间成本累积曲线”必然包络在由关键工作都按最早开始时间开始和关键工作都按最迟必须开始时间开始的曲线所组成的“香蕉图”内","2021\u002F2020教材P108页 因为在进度计划的非关键路线中存在许多有时差的工序或工作，因而Ｓ形曲线（成本计划值曲线）必然包络在由全部工作（而不是“关键工作”）都按最早开始时间开始和全部工作（而不是“关键工作”）都按最迟必须开始时间开始的曲线所组成的“香蕉图”内，故选项D不正确；也因此得知每个工程都可以有若干条“时间-成本累积曲线”，故A、C不正确；每一条S形曲线都对应某一特定的工程进度计划，故B选项正确。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]