[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118450":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1118450,789,1,"单选题","关于赢得值法中的进度偏差，表述不正确的是()。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","当进度偏差为负值时，表示进度延误",false,{"key":16,"text":17,"correct":14},"B","进度偏差=已完工作预算费用-计划工作预算费用",{"key":19,"text":20,"correct":14},"C","当进度偏差为正值时，表示进度提前",{"key":22,"text":23,"correct":24},"D","进度偏差=已完工作预算费用-已完工作实际费用",true,"2021\u002F2020教材P112页 费用偏差=已完成工作预算费用-已完成工作实际费用",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]