[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118449":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1118449,789,1,"单选题","某地下工程合同约定，计划1月份开挖土方80000立方米，2月份开挖160000立方米，合同单价均为85元\u002F立方米；计划3月份完成混凝土工程量500立方米，4月份完成450立方米，合同单价均为600元\u002F立方米。而至各月底，经确认的工程实际进展情况为，1月份实际开挖土方90000立方米，2月份开挖180000立方米，实际单价均为72元\u002F立方米；3月份和4月份实际完成的混凝土工程量均为400立方米，实际单价700元\u002F立方米。到2月底，该工程的以工作量表示的进度偏差(SV)为()万元。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","170",false,{"key":16,"text":17,"correct":14},"B","-170",{"key":19,"text":20,"correct":21},"C","255",true,{"key":23,"text":24,"correct":14},"D","-255","2021\u002F2020教材P112页 SV=BCWP-BCWS=(90000+180000)×85-(80000+160000)×85=255万元。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]