[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118448":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1118448,789,1,"单选题","下列合同实施偏差的调整措施中，属于组织措施的是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","增加人员投入",true,{"key":16,"text":17,"correct":18},"B","增加资金投入",false,{"key":20,"text":21,"correct":18},"C","变更技术方案",{"key":23,"text":24,"correct":18},"D","变更合同条款","2021\u002F2020教材P100页 组织措施是从施工成本管理的组织方面采取的措施。施工成本控制是全员的活动，如实行项目经理责任制，落实施工成本管理的组织机构和人员，明确各级施工成本管理人员的任务和职能分工、权利和责任。B属于经济措施；C属于技术措施：D属于合同措施。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]