[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118442":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1118442,789,1,"单选题","价格调整公式中的各可调因子、定值和变值权重，以及基本价格指数及其来源在()价格指数和权重表中约定。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","投标报价说明",false,{"key":16,"text":17,"correct":14},"B","合同专用条款",{"key":19,"text":20,"correct":21},"C","投标函附录",true,{"key":23,"text":24,"correct":14},"D","合同补充条款","2021\u002F2020教材P80页 价格调整公式中的各可调因子、定值和变值权重，以及基本价格指数及其来源在投标函附录价格指数和权重表中约定。价格指数应首先采用工程造价管理机构提供的价格指数，缺乏上述价格指数时，可采用工程造价管理机构提供的价格代替。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]