[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118441":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1118441,789,1,"单选题","某工程由于设计变更，工程师签发了停工一个月的暂时停工令，承包商可索赔的费用是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","租赁机械折旧费",false,{"key":16,"text":17,"correct":18},"B","机械台班折旧费",true,{"key":20,"text":21,"correct":14},"C","自有机械台班费",{"key":23,"text":24,"correct":14},"D","承包商损失费","2021\u002F2020教材P85页 施工机械使用费的索赔包括：由于业主或监理工程师原因导致机械停工的窝工费。窝工费的计算，如系租赁设备，一般按实际租金和调进调出费的分摊计算；如系承包人自有设备，一般按台班折旧费计算，而不能按台班费计算，因台班费中包括了设备使用费。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]