[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118437":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1118437,789,1,"单选题","某独立土方工程按现行工程量清单计价规范计价，招标文件中预计工程量为1万m3，合同中规定：土方工程单价为30元\u002Fm3，当实际工程量超过估计工程量10%时，超出部分价格调整为25元\u002Fm3。该工程完成后实际工程量为1.2万m3，则该土方工程的结算工程款为()万元。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","30",false,{"key":16,"text":17,"correct":14},"B","32.5",{"key":19,"text":20,"correct":21},"C","35.5",true,{"key":23,"text":24,"correct":14},"D","36","2021\u002F2020教材P78页 同例题一样结算工程价款=1×(1+10%)×30+(1.2-1.1)×25=35.5万元。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]