[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118436":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1118436,789,1,"单选题","某基础工程包含土石方和混凝土两个子项工程，工程量清单中的土石方工程量为5000m3，混凝土工程量为2500m3，合同约定：土石方工程综合单价为80元\u002Fm3，混凝土工程综合单价为450元\u002Fm3；工程预付款额度为合同价的15%，则该工程预付款额度为()万元。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","17.1",false,{"key":16,"text":17,"correct":14},"B","17.55",{"key":19,"text":20,"correct":14},"C","20.25",{"key":22,"text":23,"correct":24},"D","22.875",true,"2021\u002F2020教材P88页 预付款的支付与抵扣合同总额P=5000×80+2500×450=152.5万元；工程预付款额度=152.5×15%=22.875万元。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]