[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118431":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1118431,789,1,"单选题","根据《建设工程工程量清单计价规范》(GB50500-2013)，下列费用不属于投标人所填报的分部分项工程综合单价的是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","规费",true,{"key":16,"text":17,"correct":18},"B","利润",false,{"key":20,"text":21,"correct":18},"C","管理费",{"key":23,"text":24,"correct":18},"D","直接工程费","2021\u002F2020教材P64页 《计价规范》中的工程量清单综合单价是指完成一个规定计量单位的分部分项工程量清单项目或措施清单项目所需的人工费、材料费、施工机械使用费和企业管理费与利润，以及一定范围内的风险费用。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]