[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118427":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1118427,789,1,"单选题","建设工程人工定额中的时间定额一般不包括()。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","准备与结束时间",false,{"key":16,"text":17,"correct":14},"B","基本工作时间",{"key":19,"text":20,"correct":14},"C","辅助工作时间",{"key":22,"text":23,"correct":24},"D","多余和偶然时间",true,"2021\u002F2020教材P61页 就是某种专业、某种技术等级的工人班组或个人，在合理的劳动组织和合 理使用杞料#条件下，完成单位合格产品所必需的工作时间， 包括准备与结束时间、基本 工作时间、 辅助工作时间 、不可避免的中断时间及工人必需的休息时间。时间定额以工日 为单位，每一工日按 8h 计算。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]