[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118422":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1118422,789,1,"单选题","斗容量为1m3的反铲挖土机,挖三类土,装车,深度在3m内,小组成员4人,机械台班产量为3.84(定额单位100m3),则挖100m3的人工时间定额为( )工日。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","3.84",false,{"key":16,"text":17,"correct":14},"B","0.78",{"key":19,"text":20,"correct":14},"C","0.26",{"key":22,"text":23,"correct":24},"D","1.04",true,"2021\u002F2020教材P63页 单位产品时间定额=小组成员总人数\u002F机械台班产量=4\u002F3.84=1.04工日。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]