[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118410":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1118410,789,1,"单选题","根据竣工结算的计价原则，措施项目中的总价项目除（）外，其他应依据合同约定的项目和金额计算；如发生调整的，以发承包双方确认调整的金额计算。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","安全文明施工费",true,{"key":16,"text":17,"correct":18},"B","夜间施工费",false,{"key":20,"text":21,"correct":18},"C","二次搬运费",{"key":23,"text":24,"correct":18},"D","冬雨期施工费","2021\u002F2020教材P92页 (2)措施项目中的总价项目应依据合同约定的项目和金额计算，如发生调整的，以发承包双方确认调整的金额计算，其中安全文明施工费应按国家或省级、行业建设主管部门的规定计算。@##",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]