[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118407":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1118407,789,1,"单选题","下列属于施工成本计划数量指标的是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","按子项汇总的工程项目计划总成本指标",true,{"key":16,"text":17,"correct":18},"B","施工项目总成本降低率",false,{"key":20,"text":21,"correct":18},"C","工程项目成本降低额",{"key":23,"text":24,"correct":18},"D","设计预算成本计划降低额","2021\u002F2020教材P104页 成本计划的数量指标包含 1)按子项汇总的工程项目计划总成本指标， 2）按人工、材料、机械等各主要要素计划成本指标， 3）按分部汇总的各单位工程（或子项目）计划成本指标。@##",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]