[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118405":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1118405,789,1,"单选题","下列造成工程成本费用偏差的原因中，属于建设项目业主原因的是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","法规变化、社会原因",false,{"key":16,"text":17,"correct":18},"B","组织不落实、建设手续不全",true,{"key":20,"text":21,"correct":14},"C","设计标准化、设计保守",{"key":23,"text":24,"correct":14},"D","人工、材料、设备涨价","2021\u002F2020教材P122页 人工、材料、设备涨价属于物价上涨因素；法规变化、社会原因属于客观原因；设计标准化、设计保守属于设计原因；而组织不落实、建设手续不全属于业主原因 。@##",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]