[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118400":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1118400,789,1,"单选题","某工程每月所需混凝土量相同，混凝土用量为4000m3,计划5个月完成，混凝土综合价格为1000元\u002Fm3;实际混凝土用量为6000m3,用时6个月，从第1个月至第6个月各月混凝土价格指数（%）为100,115,110,105,115,120。则根据赢得值法，前4个月的费用偏差为（）万元。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","-30",true,{"key":16,"text":17,"correct":18},"B","-45",false,{"key":20,"text":21,"correct":18},"C","-22",{"key":23,"text":24,"correct":18},"D","-20","2021\u002F2020教材P112页 费用偏差(CV)=已完工作预算费用(BCWP)-已完工作实际费用(ACWP)前四个月的已完工作量=(6000÷6)×4=4000m3;根据题中所给出的价格指数，前四个月的实际费用分别为：1000×100%=1000元\u002Fm3;1000×115%=1150元\u002Fm3;1000×110%=1100元\u002Fm3;1000×105%=1050元\u002Fm3。费用偏差(CV)=4000×1000-(1000×1000+1000×1150+1000×1100+1000×1050)=-30万元。@##",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]