[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118390":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1118390,789,1,"单选题","有关分部分项工程成本分析的资料来源的说法正确的是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","预算成本来自投标报价成本",true,{"key":16,"text":17,"correct":18},"B","实际成本来自施工预算",false,{"key":20,"text":21,"correct":18},"C","目标成本来自施工任务单的实际工程量、实耗人工和限额领料单的实耗材料",{"key":23,"text":24,"correct":18},"D","预算成本来自施工预算","2021\u002F2020教材P122页 分部分项工程成本分析的资料来源是：预算成本来自投标报价成本，目标成本来自施工预算，实际成本来自施工任务单的实际工程量、实耗人工和限额领料单的实耗材料。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]