[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118388":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1118388,789,1,"单选题","施工成本分析的方法中，通过技术经济指标的对比，检查目标的完成情况，分析产生差异的原因，进而挖掘内部潜力的方法是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","比较法",true,{"key":16,"text":17,"correct":18},"B","因素分析法",false,{"key":20,"text":21,"correct":18},"C","差额计算法",{"key":23,"text":24,"correct":18},"D","比率法","2021\u002F2020教材P118页 比较法，又称“指标对比分析法”，就是通过技术经济指标的对比，检査目标的完成情况，分析产生差异的原因，进而挖掘内部潜力的方法。这种方法，具有通俗易懂、简单易行、便于掌握的特点，因而得到了广泛的应用，但在应用时必须注意各技术经济指标的可比性。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]