[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118384":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1118384,789,1,"单选题","某分项工程的混凝土成本数据如下（产量的目标值为800立方，实际的目标责任为850立方；单价的目标值为600元，实际值为640元；损耗率的目标为4%，实际值为3%）。应用因素分析法分析各因素对成本的影响程度，则可得出由于产量提高增加的成本是（）万元。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","10880",false,{"key":16,"text":17,"correct":14},"B","35700",{"key":19,"text":20,"correct":21},"C","31200",true,{"key":23,"text":24,"correct":14},"D","56320","2021\u002F2020教材P120页 产量提高增加成本=(850-800)×600×（1+4%）=31200",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]