[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118379":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1118379,789,1,"单选题","分部分项工程成本的分析过程中，实际偏差的获得是比较()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","实际成本与实际收入",false,{"key":16,"text":17,"correct":18},"B","实际成本与施工预算成本",true,{"key":20,"text":21,"correct":14},"C","实际成本与概算成本",{"key":23,"text":24,"correct":14},"D","实际成本与估算成本","2021\u002F2020教材P122页 (1)通过实际成本与预算成本的对比，分析当月（季）的成本降低水平;通过累计实际成本与累计预算成本的对比，分析累计的成本降低水平，预测实现项目成本目标的前景。实际成本是实际发生的工料机等的费用；预算成本来自投标报价；目标成本是来自施工预算。成本的实际偏差是通过实际成本与目标成本的比较而获得的 。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]