[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118376":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1118376,789,1,"单选题","进行分部分项工程成本分析时，需分别计算实际偏差和目标偏差，其中实际偏差的获得是比较（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","实际成本与计划成本",false,{"key":16,"text":17,"correct":18},"B","实际成本与预算成本",true,{"key":20,"text":21,"correct":14},"C","实际成本与概算成本",{"key":23,"text":24,"correct":14},"D","实际成本与估算成本","2021\u002F2020教材P122页 1.分部分项工程成本分析分部分项工程成本分析是施工项目成本分析的基础，分部分项工程成本分析的对象为已完分部分项工程，分析的方法是：进行预算成本、目标成本和实际成本的“三算”对比，分别计算实际成本与预算成本，实际成本与目标成本的偏差，分析偏差产生的原因，为今后的分部分项工程成本寻求节约途径。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]