[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118370":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1118370,789,1,"单选题","施工成本核算中的“三同步”是指()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","计划成本、目标成本和实际成本同步",false,{"key":16,"text":17,"correct":18},"B","形象进度、产值统计、实际归集成本",true,{"key":20,"text":21,"correct":14},"C","成本核算资料（成本信息）与目标成本、预算成本同步",{"key":23,"text":24,"correct":14},"D","形象进度、统计施工产值和实际成本归集均应是相同的数值","2021\u002F2020教材P115页 项目成本核算应坚持形象进度、产值统计、实际归集成本同步的原则",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]