[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118363":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1118363,789,1,"单选题","施工形象进度、产值统计、实际成本归集的三者之间的()是一致的。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","取值范围",true,{"key":16,"text":17,"correct":18},"B","施工成本",false,{"key":20,"text":21,"correct":18},"C","工程量",{"key":23,"text":24,"correct":18},"D","措施项目费","2021\u002F2020教材P115页 项目成本核算应坚持形象进度、产值统计、成本归集同步的原则，即三者的取值范围应是一致的。形象进度表达的工程量、统计施工产值的工程量和实际成本归集所依据的工程量均应是相同的数值。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]