[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118362":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1118362,789,1,"单选题","关于赢得值法中的费用绩效指数，表述不正确的是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","费用绩效指数=已完工作预算费用／计划工作预算费用",true,{"key":16,"text":17,"correct":18},"B","当费用绩效指数CPI>I时，表示节支，即实际费用低于预算费用",false,{"key":20,"text":21,"correct":18},"C","当费用绩效指数CPI＜I时，表示超支，即实际费用高于预算费用",{"key":23,"text":24,"correct":18},"D","费用绩效指数=已完工作预算费用／已完工作实际费用","2021\u002F2020教材P112页 费用绩效指数（CPI）=已完工作预算费用（BCWP)已完工作实际费用（ACWP)。@##",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]