[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118361":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1118361,789,1,"单选题","某土方工程月计划工程量2800m3，预算单价25元\u002Fm3，到月末时已完工程量3000m3，实际单价26元\u002Fm3。对该工程采用赢得值法进行偏差分析的下列说法，正确的是（）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","已完工程实际费用为75000元",false,{"key":16,"text":17,"correct":14},"B","费用绩效指数＞1,表明项目运行超出预算费用",{"key":19,"text":20,"correct":14},"C","进度绩效指数＜1，表明实际进度比计划加快",{"key":22,"text":23,"correct":24},"D","费用偏差为-3000元，表明项目运行超出预算费用",true,"2021\u002F2020教材P112页 费用偏差=已完工作预算费用-已完工作实际费用=（25-26）×3000=-3000元。当费用偏差为负值，即表示项目运行超出预算费用。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]