[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118359":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1118359,789,1,"单选题","某地下工程施工合同约定，计划4月份完成混凝土工程量450立方米，合同单价均为600元\u002F立方米。该工程4月份实际完成的混凝土工程量为400立方米，实际单价700元\u002F立方米。至4月底，该工程的进度绩效指数(SPI)为()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","0.857",false,{"key":16,"text":17,"correct":18},"B","0.889",true,{"key":20,"text":21,"correct":14},"C","1.125",{"key":23,"text":24,"correct":14},"D","1.167","2021\u002F2020教材P112页 进度绩效指数(SPI)=已完工作预算费用(BCWP)／计划工作预算费用(BCWS)=（400×600）\u002F（450×600）=0.889。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]