[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118358":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1118358,789,1,"单选题","下列施工成本控制依据中，能提供工程实际完成量及工程款实际支付情况的是（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","工程承包合同",false,{"key":16,"text":17,"correct":14},"B","施工成本计划",{"key":19,"text":20,"correct":21},"C","进度报告",true,{"key":23,"text":24,"correct":14},"D","工程变更文件","2021\u002F2020教材P109页 3.进度报告提供了每一时刻工程实际完成量，工程施工成本实际支付情况等重要信息。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]