[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118356":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1118356,789,1,"单选题","按项目组成编制施工成本计划，首先要把项目总施工成本分解到( )中。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","单体工程和单项工程",false,{"key":16,"text":17,"correct":14},"B","分部工程和分项工程",{"key":19,"text":20,"correct":21},"C","单项工程和单位工程",true,{"key":23,"text":24,"correct":14},"D","单项工程和分部分项工程","2021\u002F2020教材P107页 按项目组成编制施工成本计划，首先要把项目总施工成本分解到单项工程和单位工程中，再进一步分解为分部工程和分项工程。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]