[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118355":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1118355,789,1,"单选题","某地下工程合同约定，计划1月份开挖土方60000m3，2月份开挖140000m3，合同单价均为85元\u002Fm3；计划3月份完成混凝土工程量500m3，4月份完成450m3，合同单价均为600元\u002Fm3。而至月底，经确认的工程实际进展情况为，1月份实际开挖土方70000m3，2月份开挖160000m3，实际单价均为72元\u002Fm3；3月份和4月份实际完成的混凝士工程量均为400m3，实际单价700元\u002Fm3。到4月底，该工程的进度绩效指数(SPI)为()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","0.926",false,{"key":16,"text":17,"correct":14},"B","1.086",{"key":19,"text":20,"correct":21},"C","1.140",true,{"key":23,"text":24,"correct":14},"D","1.175","2021\u002F2020教材P112页 进度绩效指数(SPI)=已完工作预算费用(BCWP)\u002F计划工作预算费用(BCWS)=(70000×85+160000×85+400×600+400×600)\u002F(60000×85+140000×85+500×600+450×600)=1.140。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]