[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118354":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1118354,789,1,"单选题","某工程施工至某月底，经偏差分析得到费用偏差(CV)＜0，进度偏差(SV)＜0，则表明()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","已完工程实际费用节约",false,{"key":16,"text":17,"correct":14},"B","已完工程实际进度超前",{"key":19,"text":20,"correct":21},"C","已完工程实际费用＞已完工作预算费用",true,{"key":23,"text":24,"correct":14},"D","计划工作预算费用＞已完工作实际费用","2021\u002F2020教材P112页 1.费用偏差当费用偏差(CV)为负值时，即表示项目运行超出预算费用；当费用偏差(CV）为正值时，表示项目运行节支，实际费用没有超出预算费用。当进度偏差(SV)为负值时，表示进度延误，即实际进度落后于计划进度；当进度偏差(SV)为正值时，表示进度提前，即实际进度快于计划进度。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]