[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118353":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1118353,789,1,"单选题","施工成本控制的依据中，()提供了每一时刻工程实际完成量，工程施工成本实际支付情况等重要信息。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","施工成本计划",false,{"key":16,"text":17,"correct":14},"B","工程变更文件",{"key":19,"text":20,"correct":14},"C","施工组织设计",{"key":22,"text":23,"correct":24},"D","进度报告",true,"2021\u002F2020教材P109页 进度报告提供了每一时刻工程实际完成量，工程施工成本实际支付情况等重要信息。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]