[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118352":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1118352,789,1,"单选题","关于竞争性成本计划、指导性成本计划和实施性成本计划三者区别的说法,正确的是()。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","指导性成本计划是项目施工准备阶段的施工预算成本计划,比较详细",false,{"key":16,"text":17,"correct":14},"B","实施性成本计划是选派项目经理阶段的预算成本计划",{"key":19,"text":20,"correct":14},"C","指导性成本计划是以项目实施方案为依据编制的",{"key":22,"text":23,"correct":24},"D","竞争性成本计划是项目投标和签订合同阶段的估算成本计划,比较粗略",true,"2021\u002F2020教材P101页 指导性成本计划即选派项目经理阶段的预算成本计划,是以合同标书为依据,按照企业的预算定额标准指定的设计预算成本计划;实施性计划成本即项目施工准备阶段的施工预算成本计划;竞争性成本计划即工程项目投标及签订合同阶段的估算成本计划,总体上较为粗略。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]