[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118350":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1118350,789,1,"单选题","某分项工程计划工程量3000m3，计划成本15元\u002Fm3，实际完成工程量2500m3，实际成本20元\u002Fm3，则该分项工程的施工进度偏差为()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","拖后7500元",true,{"key":16,"text":17,"correct":18},"B","提前7500元",false,{"key":20,"text":21,"correct":18},"C","拖后12500元",{"key":23,"text":24,"correct":18},"D","提前12500元","2021\u002F2020教材P112页 已完工作预算费用(BCWP)=已完成工作量×预算单价=2500×15=37500元；计划工作预算费用（BCWS）=计划工作量×预算单价=3000×15=45000元；进度偏差(SV)=BCWP－BCW=37500－45000=-7500元，SV为负值，表示进度延误。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]