[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118347":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1118347,789,1,"单选题","某地下工程施工合同约定，计划1月份开挖土方80000m3，合同单价均为85元\u002Fm3。至1月底，经确定实际开挖土方90000m3，实际单价为72元\u002Fm3，则该工程的费用偏差（CV）为（）万元。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","117",true,{"key":16,"text":17,"correct":18},"B","-117",false,{"key":20,"text":21,"correct":18},"C","85",{"key":23,"text":24,"correct":18},"D","-85","2021\u002F2020教材P112页 费用偏差CV=已完工作预算费用（BCWP）-已完工作实际费用（ACWP）=90000×(85-72)=117万元。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]