[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118345":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1118345,789,1,"单选题","某地下工程施工合同约定，第一个月计划完成开挖土方70000m3，计划单价为80元／m3，经确认第一个月实际完成开挖土方80000m3，实际单价为72元／m3，则该工程的费用偏差和费用绩效指数分别为()",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","56万元，1.13",false,{"key":16,"text":17,"correct":18},"B","64万元，1.11",true,{"key":20,"text":21,"correct":14},"C","-56万元，0.9",{"key":23,"text":24,"correct":14},"D","-64万元，0.9","2021\u002F2020教材P112页 CPI=BCWP\u002FACWP=80×80000\u002F(72×80000)=1.11，而CV=BCWP-ACWP=80×80000-(72×80000)=8×80000=64万",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]