[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118343":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1118343,789,1,"单选题","关于按施工项目组成编制施工成本计划的说法，正确的是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","按成本构成分解为人工费、材料费、施工机具使用费和企业管理费等，在此基础上编制施工成本计划",false,{"key":16,"text":17,"correct":18},"B","按单项工程、单位工程、分部分项工程分解项目，在此基础上具体分配成本，编制成本支出计划，从而形成详细的成本计划表",true,{"key":20,"text":21,"correct":14},"C","对施工成本目标按时间进行分解，在网络计划基础上进一步编制成本计划",{"key":23,"text":24,"correct":14},"D","按单项工程、单位工程等进行项目分解并结合项目进度计划的横道图进一步编制成本计划","2021\u002F2020教材P107页 首先要把项目总施工成本分解到单项工程和单位工程中，再进一步分解为分部工程和分项工程，在完成施工项目成本目标分解之后，接下来就要具体地分配成本，编制分项工程的成本支出计划，从而得到详细的成本计划表。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]