[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118341":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1118341,789,1,"单选题","按照项目组成编制施工成本计划，宜将项目按( )的顺序依次进行分解后，再具体地分配成本，编制成本支出计划。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","单项工程—单位工程—分部工程—分项工程",true,{"key":16,"text":17,"correct":18},"B","单项工程—分部工程—单位工程—分项工程",false,{"key":20,"text":21,"correct":18},"C","单位工程—单项工程—分部工程—分项工程",{"key":23,"text":24,"correct":18},"D","单位工程—单项工程—分项工程—分部工程","2021\u002F2020教材P107页 大中型工程项目通常是由若干单项工程构成的，而每个单项工作包括多个单位工程，每个单位工程又是由若干个分项工程所构成。因此，首先要把项目总施工基本到单项工程和单位工程中，再进一步分解为分部工程和分项工程。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]