[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118340":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1118340,789,1,"单选题","某工程项目实施过程中，已完工作预算费用曲线（BCWP）与已完工作实际费用曲线（ACWP）靠的很近，而与计划工作预算费用曲线（BCWS）离开很远，则表示该工程项目在（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","费用与进度上均是按预定计划目标进行的",false,{"key":16,"text":17,"correct":14},"B","费用与进度上均没有按预定计划目标进行的",{"key":19,"text":20,"correct":21},"C","费用上是按预定计划目标进行的",true,{"key":23,"text":24,"correct":14},"D","进度上是按预定计划目标进行的","2021\u002F2020教材P112页 费用偏差CV(Cost Variance)费用偏差(CV)=已完工作预算费用(BCWP)-已完工作实际费用(ACWP)。当费用偏差(CV)为负值时，即表示项目运行超出预算费用；当费用偏差(CV)为正值时，表示项目运行节支，实际费用没有超出预算费用。已完工作预算费用曲线与已完工作实际费用曲线靠的很近，说明费用是按预定计划目标进行。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]