[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118338":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1118338,789,1,"单选题","下列各项不属于施工成本计划的分类的是（）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","竞争性成本计划",false,{"key":16,"text":17,"correct":14},"B","指导性成本计划",{"key":19,"text":20,"correct":14},"C","实施性成本计划",{"key":22,"text":23,"correct":24},"D","目标性成本计划",true,"2021\u002F2020教材P101页 对于一个施工项目而言，其成本计划的编制是一个不断深化的过程。在这一过程的不同阶段形成的深度和作用不同，按其作用可分为三类：①竞争性成本计划；②指导性计划成本；③实施性计划成本。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]