[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118335":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1118335,789,1,"单选题","已知某工程的计划工作预算费用为5000万元，已完工作预算费用为6000万元，已完工作实际费用为5800万元，则此工程的进度绩效指数为()。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","0.7",false,{"key":16,"text":17,"correct":14},"B","0.9",{"key":19,"text":20,"correct":14},"C","1.02",{"key":22,"text":23,"correct":24},"D","1.2",true,"2021\u002F2020教材P112页 进度绩效（SPI）=已完工作预算费用（BCWP）\u002F计划工作预算费用（BCWS）=6000\u002F5000=1.2",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]